VT II Specific
Rating
0
0
There are no comments for now.
1.
Per SOP-11-02, the minimum light level at the examination surface for the direct technique is:
2.
Per SOP-11-02, for the direct technique the examiner's eye shall be within:
3.
Per SOP-11-02, the viewing angle for the direct technique shall be:
4.
Per SOP-11-02, who rules on a doubtful indication?
5.
Per SOP-11-02 and B31.3 (2024) 344.2.2, remote VT may be used on B31.3 work only when:
6.
Per SOP-11-02, a light reading taken with a phone lux app is:
7.
Per SOP-11-02, the white light meter shall be calibrated:
8.
Per SOP-11-04, near vision for VE personnel shall be demonstrated:
9.
Per SOP-11-04, the minimum formal VE training for a Level II candidate is:
10.
Per SOP-11-04, the minimum experience for VE Level II is:
11.
Per SOP-11-04, to pass certification examinations, a candidate needs:
12.
Per SOP-11-04, the VE Level II certification period is:
13.
Per SOP-11-02 and B31.3 (2024) 342.2, in-process VT shall be performed by:
14.
Per SOP-11-02, a weld examined with no relevant indication is recorded as:
15.
Per SOP-11-02, VT of the weld surface is performed:
16.
Per SOP-11-02, a change from the direct technique to the remote technique is classified as:
17.
Per SOP-11-02, who may perform, evaluate and sign VT results?
18.
Per SOP-11-02, when a rejectable condition is found, the examiner shall:
19.
Per SOP-11-04, the leak testing included in every VE qualification does NOT cover:
20.
Per SOP-11-04, a VE Level II who has not performed VE for 12 consecutive months or more: